Application Debugging After the Upgrade
If you properly execute your test plan, all critical functions will work after the upgrade. Less critical functions, however, may contain bugs. Be prepared to fix these bugs for a period after the upgrade. (Two weeks is usually long enough.) During this time, avoid scheduling new feature development. Have streamlined change control procedures ready, so that fixes can be installed quickly if a problem occurs.