The Migration Plan
The process of migrating to the latest version of OpenROAD can involve simply migrating the software and performing some basic tests. However, for a more complex or sizable OpenROAD installation, we recommend creating a project plan from which to execute the migration. For example, migrating from older releases requires additional information, which you can find in
Migration Considerations for OpenROAD Releases.
This section suggests areas to consider when planning a migration. It is not intended as a definitive migration plan, but as a guide to creating one. Your actual plan will depend on the scale, complexity, and methodologies of the installation and your business.
The process of developing a migration plan consists of the following basic stages:
1. Initiation
2. Testing
3. Backout strategy
4. Migration scheduling
5. Live rollout
6. Plan creation